DONG

DONG

Over 20 years' experience of offshore wind farm development makes DONG Energy the current market leader in offshore wind power. The majority of DONG Energy's wind farms are based in north-west Europe, and we have built more wind farms than any other company in the world.

DONG Energy aims to supply clean and reliable energy. We develop, build and run wind farms and are well on the way to reaching the target of a minimum wind capacity of 3,000 MW in 2020.  We currently have 1,035 MW of on and offshore wind power in operation and 1,316 MW under construction. In 2010 14.5% of DONG Energy's power production came from wind power.

Barrow

Renewable Energy Asset Name:Barrow Offshore Wind Farm
Location:Irish Sea
Landing Point of Export Cable:Heysham
Distance From Shore (Miles):4.3 miles
Construction Start Date:April 2005
Commissioned Date:June 2006 - January 2007
Number of Turbines/Devices:30
Size of Area Taken Up (KM2):10
Total Capacity:90MW
Granted Safety Zones Surrounding Structures?Yes
Size of Granted Safety Zones(Metres):50
Emergency Contact08455 441037

Links:

Burbo Bank

Renewable Energy Asset Name:Burbo Bank Offshore Wind Farm
Location:Liverpool Bay
Landing Point of Export Cable:Liverpool, Wallasey
Distance From Shore (Miles):4.0
Construction Start Date:End of 2007
Commissioned Date:November 2008
Number of Turbines/Devices:25
Size of Area Taken Up (KM2):10
Total Capacity:90MW
Granted Safety Zones Surrounding Structures?yes
Size of Granted Safety Zones(Metres):50
Emergency Contact08455 440137

Links:

Gunfleet Sands

Renewable Energy Asset Name:Gunfleet Sands Offshore Wind Farm
Location:Clacton-on-Sea, Essex
Landing Point of Export Cable:Clacton
Distance From Shore (Miles):4.3
Construction Start Date:September 2008
Commissioned Date:Spring 2010
Number of Turbines/Devices:48
Size of Area Taken Up (KM2):17.5
Total Capacity:172MW
Granted Safety Zones Surrounding Structures?Yes
Size of Granted Safety Zones(Metres):50
Emergency Contact08455 441037

Links:

London Array

Renewable Energy Asset Name:London Array 1 Offshore Windfarm
Location:Ramsgate, Kent
Landing Point of Export Cable:Faversham
Distance From Shore (Miles):approx 13
Construction Start Date:March 2011
Commissioned Date:October 2012
Number of Turbines/Devices:175
Size of Area Taken Up (KM2):317
Total Capacity:630 MW
Granted Safety Zones Surrounding Structures?Yes
Size of Granted Safety Zones(Metres):50
Emergency Contact01843 855795

Links:

Walney 1

Renewable Energy Asset Name:Walney Offshore Windfarm 1 (WOW01)
Location:Irish Sea
Landing Point of Export Cable:Heysham
Distance From Shore (Miles):8.9-16 miles
Construction Start Date:April 2010
Commissioned Date:June 2011
Number of Turbines/Devices:51
Size of Area Taken Up (KM2):73 (WOW1+WOW2)
Total Capacity:183.6MW
Granted Safety Zones Surrounding Structures?Yes
Size of Granted Safety Zones(Metres):50m
Emergency Contact08455 441037

Links:

Walney 2

Renewable Energy Asset Name:Walney Offshore Windfarm 2 (WOW02)
Location:Irish Sea
Landing Point of Export Cable:Fleetwood
Distance From Shore (Miles):8.9-16 miles
Construction Start Date:April 2011
Commissioned Date:April 2012
Number of Turbines/Devices:51
Size of Area Taken Up (KM2):73 (WOW1+WOW2)
Total Capacity:183.6MW
Granted Safety Zones Surrounding Structures?Yes
Size of Granted Safety Zones(Metres):50m
Emergency Contact08455 441037

Links:

West of Duddon Sands

Renewable Energy Asset Name:West of Duddon Sands Offshore Wind Farm
Location:Irish Sea
Landing Point of Export Cable:Heysham
Distance From Shore (Miles):appox 8.5
Construction Start Date:April 2013
Commissioned Date:Under Construction
Number of Turbines/Devices:108
Size of Area Taken Up (KM2):67
Total Capacity:389MW
Granted Safety Zones Surrounding Structures?yes
Size of Granted Safety Zones(Metres):50m
Emergency ContactDuty Phone: + 44(0)78919 34877 Emergency Phone: + 44(0)78919 34907

Links:

Westermost Rough

Renewable Energy Asset Name:Westermost Rough
Location:East Riding of Yorkshire
Landing Point of Export Cable:Tunstall, East Riding of Yorkshire
Distance From Shore (Miles):9
Construction Start Date:2014
Commissioned Date:2015
Number of Turbines/Devices:35
Size of Area Taken Up (KM2):35
Total Capacity:210 MW
Granted Safety Zones Surrounding Structures?Yes
Size of Granted Safety Zones(Metres):50
Emergency Contact08455 441037

Links: