Subsea Cables

print this page

Uk - Germany - Cable Recovery

The CS Wave Sentinel will be conducting 16km cable recovery of the UK-Germany 6 cable system situated within UK EEZ. The recovery will commence at approx. 05:00 am on the 17th of February and will take approximately 1 day.

 

UK-Germany 6  16km Reecovery from Position:

54°26.025'N 000°22.145'E

To Approximate Position:

54°30.342'N 000°35.004'E

Marine operations will be running from 17th February for 1 day depending upon operational and weather conditions.

For further information, please contact: Alex Riddell, Global Marie Systems Ltd, Tel +44 1245 702111  email: alex.riddell@globalmarinesystems.com

 

 

 