Concerto North - Cable Repair

 

The CS Sovereign is currently scheduled to arrive on site 03 January 2018 to commence repair works.

The estimated location is 52° 17.25'N 002° 18.62'E,

and the duration of the cable repair will be approximately 5 days depending upon weather or other operational conditions. Departure is currently scheduled for today, but weather is being monitored and there is possibility of delay if wind prevents safe working conditions.

 

For further information: John Wrottesley, Global Marine Group, Tel: +44 1245 702009 email: john.wrottesley@globalmarine.group